Gas Turbine Inlet Silencer Repair for a Virginia Power Plant

GSM Industrial removed, repaired, and reinstalled a gas turbine inlet silencer and elbow for Envanio at a Virginia power plant.

On a gas turbine, the inlet silencer sits on the clean-air side of the filters. Rust that breaks loose there has one place to go: the compressor. At a gas-fired power plant in Virginia, the floors of the inlet silencer and the elbow downstream of it were badly corroded, and the silencer sat in the duct nearly 45 feet above grade.

GSM Industrial crew member beside a 62,000-lb gas turbine inlet silencer set on grade for corrosion repair
The inlet silencer on grade after the crew rigged it down from the duct. Every baffle is numbered so it goes back in the same position.

GSM Industrial completed a gas turbine inlet silencer repair for Envanio at a Virginia power plant, on site from April 18 to May 1, 2026. The scope covered a 62,000-pound silencer and its downstream elbow, set 44 feet 10 inches above grade, with all 26 baffles removed and reinstalled. The crew repaired severe floor corrosion, applied Sherwin-Williams Macropoxy 646 epoxy, and installed 10-gauge 304 stainless steel cladding. GSM finished one day ahead of schedule.

Project Overview

CustomerEnvanio
IndustryPower generation (gas-fired)
LocationVirginia
Project TypeGas turbine inlet silencer and elbow corrosion repair
Silencer62,000 lbs, 12 ft high x 28 ft wide x 12 ft deep, 26 internal baffles
Elevation44 ft 10 in above grade
Flange Connections124 bolts at each major flange
Floor RepairCorrosion repair welding, 6 mils Sherwin-Williams Macropoxy 646 epoxy, 10-gauge 304 stainless steel cladding
AccessCrane and rigging, scaffolding, high-reach lifts, temporary supports, barrier walls
GSM Crew4: one working foreman and safety lead, three welder-mechanics
On SiteApril 18 to May 1, 2026, one mobilization, finished one day ahead of schedule
GSM ServicesRigging, mechanical disassembly and reassembly, field welding, coating, insulation, plant maintenance

The Challenge: Corroded Steel Nearly 45 Feet Up

Severe corrosion ran across the floors of both the silencer and the downstream elbow. The steel had to be mechanically prepared before any coating or cladding could go down, and the weld repairs had to go into badly deteriorated base metal, which is slower and harder than welding sound plate. Reaching that floor meant rigging the silencer and elbow out of an elevated duct system, then pulling all 26 baffles along with their upstream and downstream stops and the bleed heat supports. Every baffle had to go back in the right position afterward.

Corroded floor and baffle bases inside a gas turbine inlet silencer before repair
The silencer floor before repair. Corrosion ran along the floor and around the base of the baffles.
Mobile crane and high-reach lift staged at a gas turbine inlet structure for silencer removal
The crane and a high-reach lift staged at the turbine inlet for the lift.

How GSM Completed the Gas Turbine Inlet Silencer Repair

GSM sent one four-person plant maintenance crew: a working foreman who also served as safety lead, and three welder-mechanics. Using a crane, scaffolding, and high-reach lifts, the crew handled the rigging, broke the 124-bolt flange connections, set the silencer and elbow down, and installed temporary supports and barrier walls around the open duct.

GSM Industrial crew working on the downstream elbow of a gas turbine inlet set on grade
The downstream elbow on grade for its own floor repair.

With the baffles out, the same crew handled the corrosion repair and field welding. The new floor combines 10-gauge 304 stainless steel cladding with 6 mils of Sherwin-Williams Macropoxy 646 epoxy. The crew also modified the bleed heat piping supports. Then they reset all 26 baffles in their original positions, reinstalled the silencer and elbow, replaced disturbed hardware, reinstalled insulation, sealed the flanges, and cleaned up. No separate rigging, welding, or coating crew came on site.

10-gauge 304 stainless steel cladding plates tacked in place on a gas turbine inlet silencer floor
New 10-gauge 304 stainless steel cladding plates fitted and tacked across the silencer floor. Each plate is marked for its position.
Silencer floor coated with white Sherwin-Williams Macropoxy 646 epoxy, baffles in place
The silencer floor after the Sherwin-Williams Macropoxy 646 epoxy coat.

The Outcome: One Day Ahead of Schedule

GSM finished on May 1, one day ahead of schedule, in a single mobilization with no scheduling issues or delays, despite the extra welding the corrosion demanded. The silencer and elbow went back in place with repaired, clad, and coated floors. Four people took a 31-ton assembly apart, fixed it, and put it back a day early.

Finished stainless steel floor cladding and welded baffle stops in a gas turbine inlet silencer
The finished stainless steel floor cladding, with the baffles back in position.

Team Quote

We didn’t have to bring in a separate rigging crew, a welding crew, a coating crew, or additional specialists every time the job changed gears. The GSM crew handled the work from disassembly through final cleanup.

Matthew Huntington, Account Manager, GSM Industrial

Similar Projects

Frequently Asked Questions

Why does corrosion inside a gas turbine inlet silencer matter?

Corrosion inside a gas turbine inlet silencer matters because the silencer sits downstream of the inlet filters, so rust and coating chips that break loose can be carried straight to the compressor. Industry guidance flags debris released on the clean-air side of the filters as a cause of compressor airfoil damage. Repairing corroded floor steel and protecting it with coatings or stainless steel cladding keeps that material in place.

Can a corroded gas turbine inlet silencer be repaired instead of replaced?

In many cases, yes: corroded silencer floor sections can be repaired, coated, and clad with stainless steel without replacing the whole silencer. On this project, GSM rigged down a 62,000-pound silencer from 44 feet 10 inches above grade, removed its 26 baffles, weld-repaired the deteriorated floor steel, protected it with 304 stainless steel cladding and epoxy, and reinstalled the assembly.

Does GSM Industrial perform power plant repairs during outages?

Yes, GSM Industrial performs plant maintenance, rigging, and field welding during planned outages, with crews that cover more than one trade. On this job, a four-person crew handled rigging, disassembly, welding, coating, cladding, reassembly, and cleanup in a single mobilization.

Planning a silencer, ductwork, or outage repair?

GSM Industrial rigs, repairs, and reinstalls silencers, ductwork, and other heavy equipment during planned outages, with crews that handle rigging, welding, and coating.

Useful details for scoping a repair: equipment size and weight, elevation, current condition and photos, outage window, coating or cladding specs, and site access.